Robinson Falls Power Station (GPS: 4.45787, 101.38963) is a power station on Sungai Bertam in Cameron Highlands. The station is located off Jalan Boh in the village of Habu, in the township of Ringlet. It is located at the end of a hill road which passes through various vegetable farms.

The Robinson Falls Power Station is the first power station to be built for the Cameron Highlands-Batang Padang HEP Schemes1, which were deviced to harnass hydroelectric from the highland rivers. Although the schemes were planned as early as the 1940s, implementation only took place in the 1950s and 1960s due to World War II and the Japanese Occupation of the country.

The Robinson Falls Power Station was the first power station of the scheme to be completed. Construction began in 19572, and the power station became operational in November, 1959. The construction of this power station was to demonstrate the use of hydroelectricity to the country.

From the 1980s through the 1990s, water catchment areas throughout Cameron Highlands experienced land clearing for vegetable farming as well as other development. The indiscriminate clearing of the forest negatively impacted the quality of water in the rivers, resulting in the high presence of clay as well as fine and medium-size sand in the water. This leads to increased sedimentation and silt depositation at the various power stations, including at the Robinson Falls Power Station.

During my visit to this power station, I do notice that the water of Sungai Bertam is still the colour of milky tea. Obviously the level of clay in the water was still very high, even in 2016.

Robinson Falls Power StationRobinson Falls Power Station (2 May, 2016)


Robinson Falls Power StationRobinson Falls Power Station (2 May, 2016)


Robinson Falls Power StationRobinson Falls Power Station (2 May, 2016)


Robinson Falls Power StationRobinson Falls Power Station (2 May, 2016)


Robinson Falls Power StationRobinson Falls Power Station (2 May, 2016)


Robinson Falls Power StationRobinson Falls Power Station (2 May, 2016)


Robinson Falls Power Station is on the map of Ringlet, Cameron Highlands

References

1. Case Study - The Siltation Issue in the Cameron Highlands-Batang Padang Hydroelectric Power Scheme, by Foon Shyong Wai and Ramli bin Abdullah.

2. UM Student Report: Annual Energy Output of Robinson Falls, Habu and Jor power stations.

Back to Cameron Highlands, Pahang mainpage; list of Government Buildings in Cameron Highlands, Government Buildings in Pahang and Government Buildings in Malaysia

 Latest updates on Penang Travel Tips

 Discover with Timothy YouTube Channel

 PG Food Channel

 Learn Penang Hokkien YouTube Channel

SojiMart Videos

Latest from Discover with Timothy: Gurney Bay - what to see and do there

About this website



Hello and thanks for reading this page. My name is Timothy and my hobby is in describing places so that I can share the information with the general public. My website has become the go to site for a lot of people including students, teachers, journalists, etc. whenever they seek information on places, particularly those in Malaysia and Singapore. I have been doing this since 5 January 2003, for over twenty years already. You can read about me at Discover Timothy. By now I have compiled information on thousands of places, mostly in Peninsular Malaysia and Singapore, and I continue to add more almost every day. My goal is to describe every street in every town in Malaysia and Singapore.

Robbie's Roadmap

Copyright © 2003-2024 Timothy Tye. All Rights Reserved.